Schedule A - With Permits · How This Works
Kimberly's Preferred Approach · Full Package · No Split
Kimberly's Deliverables - What · When · Why
What Kimberly Delivers
Space planning layouts - all Phase 1 zones
MEP coordination drawings - where plumbing and electrical go (design intent only)
Elevation drawings - all 4 walls per space
Full home lighting plan - all rooms, hallways, exterior, patio
Mood boards + color palettes - all spaces
Finish inspo boards - tile, stone, hardware, fixtures, paint (visual reference only - Windsor sources independently)
3D renders - kitchen and all bathrooms
Cabinetry and wardrobe shop drawing coordination
When & Why
Delivered as one complete package during permit review - Weeks 3–8 pre-construction
Windsor can't use them until permits are approved anyway - timing is perfect, no rush
MEP coordination drawings land before MEP rough-in (Construction Week 3)
Finish inspo lands before Windsor needs to source finishes - 4–6 weeks of lead time
Client design presentations happen during permit wait - clients stay engaged
Joe's drawing review by Kimberly happens during permit wait - all corrections before construction
Finish Inspo vs. Procurement - Important Distinction
Kimberly provides finish selection inspo as visual design reference - tile family, stone, hardware style, fixture direction. Windsor sources everything independently. Kimberly's boards give Windsor the direction to buy correctly; they do not obligate a specific vendor or SKU.
What Windsor still needs before walls close (regardless of who sources): valve type and configuration, tub type, filler location, showerhead count, vanity mount type, lighting placement, heated floor decision. These come from the Client Preference Guide → Rough-In Spec Sheet → Windsor.
What Windsor still needs before walls close (regardless of who sources): valve type and configuration, tub type, filler location, showerhead count, vanity mount type, lighting placement, heated floor decision. These come from the Client Preference Guide → Rough-In Spec Sheet → Windsor.
Construction Sequencing Logic
Demo: All zones simultaneously - one crew, one pass, one inspection round.
MEP Rough-In: All zones in one pass - plumber and electrician touch the whole house once.
Build-Out Priority: 1 · Kitchen + Open Concept (chimney removal, highest priority) 2 · Master Bath Addition (new construction) 3 · Guest Bath 1 + 2 in parallel 4 · Laundry Room 5 · Hidden Hallway Wardrobe
Glass Wall Critical Path: 90-day lead time. Order placed Week 1 regardless of permit decision. Target arrival: Construction Week 5-6.
Joe - Kimberly Dependency: Kimberly cannot finalize her technical drawings without Joe's framing plans and structural drawings first. Joe delivers to Kimberly - Kimberly reviews, incorporates, and then delivers her complete package to Windsor. Joe's deadline is the critical path for Kimberly's delivery.
MEP Rough-In: All zones in one pass - plumber and electrician touch the whole house once.
Build-Out Priority: 1 · Kitchen + Open Concept (chimney removal, highest priority) 2 · Master Bath Addition (new construction) 3 · Guest Bath 1 + 2 in parallel 4 · Laundry Room 5 · Hidden Hallway Wardrobe
Glass Wall Critical Path: 90-day lead time. Order placed Week 1 regardless of permit decision. Target arrival: Construction Week 5-6.
Joe - Kimberly Dependency: Kimberly cannot finalize her technical drawings without Joe's framing plans and structural drawings first. Joe delivers to Kimberly - Kimberly reviews, incorporates, and then delivers her complete package to Windsor. Joe's deadline is the critical path for Kimberly's delivery.
W1
Joe Finalizes Plans · Glass Panel Order · Design Begins
Pre-Construction
Windsor - GC
🚨 Order glass panels THIS WEEK - 90-day lead time. Do not wait for permits.
Confirm licensed SE (structural engineer) - required for permit submission
Begin material sourcing: cabinetry pricing, stone supplier, tile, vanities, white oak flooring
Pre-schedule all subcontractors: plumber, electrician, HVAC, tile, flooring, carpenter
◆ Glass panel order placed
Joe - Drafter
🚨 Kitchen framing plan to Windsor before demo - chimney wall connects to kitchen
🚨 Master bath framing plan delivered simultaneously - both spaces frame together
Open concept unified floor plan (post chimney removal)
Living room glass wall elevation + structural header notes
Guest bath 1 and 2 drawings
Coordinate with SE - beam specs and structural notes incorporated
🚨 Full drawing set delivered to Kimberly BEFORE she can complete her technical package - Joe delivers first, Kimberly incorporates, then delivers to Windsor
◆ Kitchen + Master bath framing plans to Windsor · Full set to Kimberly by Friday
Kimberly V - Designer
⚠ Cannot finalize MEP coordination drawings or elevations until Joe's framing plans are in hand - Joe's delivery unlocks Kimberly's technical package
Design team begins: space planning, mood boards, client presentations while awaiting Joe's drawings
Present Kitchen mood board + 3D render - collect written approval
Present Open Concept reconfiguration layout - collect written approval
Present Master Bath mood board + 3D render - collect written approval
◆ Kitchen + Open Concept + Master Bath client approvals in hand
W2
Drawing Review · SE Coordination · Permit Package Submitted
Pre-Construction
Windsor - GC
Review Joe's full drawing set - flag constructability issues
SE review of chimney wall and glass wall header - SE stamp required
Place cabinetry order (6–10 week lead time)
Reserve Calcutta Viola marble slab with stone supplier
Confirm white oak flooring order and delivery window
◆ SE stamp confirmed · Cabinetry on order · Marble slab reserved
Joe - Drafter
Incorporate Windsor + Kimberly redlines - update full drawing set
Laundry room shop drawings + MEP coordination notes
Hidden hallway wardrobe shop drawings
Full home lighting plan complete
Compile full permit package: site plan, floor plans, elevations, structural, MEP
◆ Permit package submitted to LADBS SUBMIT
Kimberly V - Designer
Design team continuing: MEP coordination, elevation drawings, material research
Review Joe's full drawing set vs design intent - redline deviations same day
Present Guest Bath 1 + 2 mood boards + 3D renders - collect approvals
Present Laundry Room design direction - collect approval
◆ Guest Bath + Laundry client approvals in hand
W3–8
City Permit Review - 4 to 8 Weeks · Full Design Package Completed
Permit Phase - Kimberly's Design Window
Windsor - GC
Monitor permit status weekly at LADBS
Respond to city plan check corrections within 48 hours
Confirm all material delivery schedules align with construction start
Confirm glass panel delivery window - target Con Week 5-6
⚠ Note: LA typically requires 1–2 rounds of plan check corrections - budget 2-week buffer
◆ Permits approved - construction start date confirmed
Joe - Drafter
Respond to city plan check corrections - revise and resubmit within 48 hours
Deliver final complete drawing set to Kimberly for design intent review FINAL
◆ All drawings finalized - Joe on RFI standby
Kimberly V - Designer
◆ THIS IS KIMBERLY'S DESIGN WINDOW - 4–8 weeks, no construction pressure
Complete MEP coordination drawings - all Phase 1 zones
Complete all elevation drawings - every wall per space
Complete full home lighting plan
Finalize all finish inspo boards - tile, stone, hardware, fixtures, paint
Complete all mood boards and finish specification boards
Complete 3D renders - kitchen and all bathrooms
Final review of Joe's complete drawing set for design intent accuracy
Lock all client approvals before construction begins
◆ FULL DESIGN PACKAGE COMPLETE - delivered to Windsor on Construction Day 1 FULL DELIVERY
CW1–2
Demo All Zones Simultaneously + Structural Framing
Construction Phase Begins
Windsor - GC
Day 1: site protection - dust barriers, floor protection, utility shutoffs
Chimney and fireplace demolition - SE on site for structural sign-off
Remove chimney wall connecting kitchen and living room
Temporary shoring during structural wall removal
Demo kitchen, guest baths 1+2, laundry - all simultaneously
Install structural beam/header - chimney zone
City structural inspection - beam sign-off
Frame master bath addition on existing footprint
Frame glass wall rough opening and structural header
⚠ Risk: Structural surprises inside chimney wall - 3–5 day buffer
Joe - Drafter
Field RFI responses - 24-hour turnaround throughout construction
Verify framing matches drawings after beam installation
Update drawings for any field-required structural modifications - same-day
Kimberly V - Designer
◆ Day 1: full design package handed to Windsor - MEP drawings, elevations, lighting plan, finish inspo FULL DELIVERY
Day 1 site kickoff - walk all Phase 1 zones, confirm sequencing
Site visit Week 2 - verify framing matches design drawings
Friday client update - chimney down, space opening up
CW3–4
MEP Rough-In All Zones + Inspections + Drywall
Rough-In Phase
Windsor - GC
Kitchen rough plumbing: sink, dishwasher, gas line, pot filler if applicable
Kitchen rough electrical: new circuits, under-cabinet lighting, island
Master bath: full plumbing rough-in per approved drawings + rough-in spec sheet
Guest Bath 1 + 2: plumbing rough-in
Laundry room: plumbing and electrical rough-in
Full home electrical rough-in per approved lighting plan
MEP inspections - schedule Monday morning
Insulation all zones
Drywall hanging - all Phase 1 zones
⚠ Risk: Failed MEP inspection most common delay - budget 3-day correction window
Joe - Drafter
Verify MEP rough-in matches drawings - flag conflicts to Kimberly same day
Revised sheets for any field MEP changes - same day REVISED
Deliver confirmed full house spatial floor plan FINAL
Deliver confirmed full home lighting plan FINAL
Kimberly V - Designer
Site visit: verify MEP rough-in matches design drawings before walls close
Flag any MEP deviation from design intent to Windsor in writing - same day
Confirm all material deliveries on track: tile, vanities, fixtures, hardware, flooring
Halfway client check-in - progress update, upcoming milestones
Stone fabricator: confirm countertop templating for Con W6
CW5–6
Tile + Cabinetry + Glass Wall Install + Flooring Begins
Finishes Phase
Windsor - GC
Drywall taping, mudding, sanding - all zones
Waterproofing + backer board: master bath shower, guest bath showers
Tile: master bath shower walls + floor
Guest bath 1 + 2 tile installation
Laundry room tile + cabinetry
Hallway wardrobe carpenter on site - built-in installation
Kitchen cabinetry installation
Master bath + guest bath vanity cabinet installations
Living room glass panel wall installation
White oak flooring begins - open concept zone first
⚠ Risk: Glass panels must arrive by start of Week 6 or install slides into Week 7
Joe - Drafter
Field RFI responses - 24-hour turnaround
Cabinetry cross-check: confirm installed position matches shop drawings
Document field changes - compile final as-built set
Kimberly V - Designer
Site visit: tile matches approved inspo spec before grout sets
Inspect waterproofing before tile goes on top
Cabinetry inspection - verify against elevations, confirm hardware placement
Glass wall inspection - plumb, level, smooth operation
Stone fabricator on site for countertop field measurement - all zones
Review wardrobe carpenter progress vs shop drawings
Friday client update - milestone photos per photography protocol
CW7–8
Countertops + Fixtures + Paint + Punch List + Handover
Completion Phase
Windsor - GC
Countertop installation - Calcutta Viola marble all zones
Plumbing fixture trim-out: faucets, showerheads, toilets, sinks - all zones
Electrical trim-out: switches, outlets, all lighting fixtures per lighting plan
Door hardware installation throughout
White oak flooring completion - all remaining zones
Laundry room appliance connections
Prime coat then final paint - all Phase 1 zones
Final plumbing + electrical inspections
Punch list corrections - 48-hour window
Deep clean all Phase 1 zones
Certificate of occupancy / final inspection sign-off
Joe - Drafter
Deliver final as-built drawing package to Kimberly + Windsor FINAL AS-BUILT
Same-day punch list drawing corrections if required
◆ Final as-built delivered to clients CLIENT COPY
Kimberly V - Designer
Countertop inspection - seam placement, stone quality, overhang per spec
Verify all lighting fixtures installed + centered per approved lighting plan
On-site paint color confirmation with Windsor before final coat
Full designer punch list walk - document all items with photos
Deliver punch list to Windsor in writing - 48-hour correction window
Joint client walkthrough with Windsor - present completed Phase 1 spaces
◆ Written client final approval - triggers final payment ($7,900 due within 48 hours)
✓
Phase 1 Punch List
Final Inspection - Check Off Each Item Before Sign-Off
How to use: Kimberly walks the site and checks off each item. Anything unchecked gets delivered to Windsor in writing. Windsor has 48 hours to correct. Client signs off once all items are complete. Tags show who is responsible.
Kitchen
All cabinet doors align and close without resistance GC
Cabinet hardware at correct height per elevations DESIGNER
Countertop seams clean, no visible gaps or chips GC
Backsplash tile grout uniform and sealed GC
Sink faucet operational, no leaks under cabinet GC
All appliances connected, tested, operational GC
Under-cabinet lighting on correct switch and dimmer GC
Island lighting centered per approved lighting plan DESIGNER
Open concept flow reads as unified space DESIGNER
White oak flooring: no gaps, scratches, or unevenness GC
Paint lines clean at ceiling and all trim GC
Master Bath Addition
Shower tile grout sealed, no lippage between tiles GC
Shower door/glass plumb and operates smoothly GC
Showerhead height correct per approved elevation DESIGNER
Double vanity faucets operational, no leaks GC
Vanity mirrors and lighting centered per elevation DESIGNER
Toilet level, no movement, sealed to floor GC
Exhaust fan operational and vented to exterior GC
Waterproofing inspection documented in as-built DRAFTER
Floor transition to bedroom flush and clean GC
Guest Bath 1 & 2
Shower tile and grout sealed per spec GC
Vanity faucet and drain operational, no leaks GC
Toilet level and sealed to floor GC
Lighting centered on vanity wall per elevation DESIGNER
Exhaust fan vented to exterior and operational GC
Cabinet doors aligned, hardware installed GC
Paint clean at tile line and ceiling GC
Mirror centered at correct height per design DESIGNER
Laundry Room
Washer/dryer connections operational - hot, cold, drain GC
Dryer vent ducted to exterior GC
Cabinetry installed level and aligned GC
Finishes match approved design direction DESIGNER
Lighting on correct switch and operational GC
Floor finish complete and clean GC
Living Room - Glass Wall
Glass panels plumb and level in opening GC
All panels slide smoothly on track, no binding GC
Weatherstripping sealed when panels are closed GC
Structural header inspection documented in as-built DRAFTER
Interior trim around opening clean and painted GC
Floor transition at threshold flush and clean GC
Lighting per plan, dimmers functioning DESIGNER
Hidden Hallway Wardrobe
Panel reads as wall when closed - no visible gap DESIGNER
Panel opens and closes smoothly, mechanism reliable GC
Interior layout matches shop drawings DRAFTER
Interior lighting operational GC
Finish matches surrounding hallway exactly DESIGNER
No visible seam at panel edges when closed GC
Whole Home
White oak flooring: no squeaks, gaps, or surface damage throughout GC
Full home lighting plan: all fixtures operational per approved zones DESIGNER
All dimmers functioning correctly GC
Paint: no roller marks, drips, or missed spots in any room GC
All doors open and close without sticking GC
HVAC operational in all zones, vents unobstructed GC
All final inspections passed, certificates on file GC
Final as-built drawing package delivered to clients DRAFTER
Site deep cleaned, no construction debris remaining GC
Written client final approval collected - final payment triggered DESIGNER
◆
Schedule B - Fast Track · How the Split Delivery Works
No Permits · Demo Starts Immediately · Building Docs Day 1 · Selections Week 3
Phase 1 Delivery - Building Documents · Day 1 Before Demo Begins
What's Delivered Day 1
Space planning layouts - all Phase 1 zones
Kitchen framing layout - chimney wall connects here
Master bath addition layout - new construction
MEP coordination drawings - where plumbing and electrical go
Elevation drawings - structural positions and dimensions
Shop drawings for wardrobe and cabinetry
Why This Is Enough to Build
Windsor can frame, rough-in MEP, and close walls with these alone. He does not need the tile color to run a pipe.
Rough-in critical items (valve type, tub filler location, vanity mount, lighting placement) come from the Client Preference Guide → Rough-In Spec Sheet → Windsor. These are separate from finish inspo.
Phase 2 Delivery - Design Selections · Week 3 Start · Before Windsor Needs Finishes
What's Delivered Week 3
Mood boards + color palettes - all spaces
Finish inspo boards - tile, stone, hardware, fixtures, paint (visual reference - Windsor sources independently)
3D renders - kitchen and all bathrooms
Full home lighting plan
Client design presentations - Week 3 while framing is going up
Why Week 3 Timing Is Intentional
Tile goes in Week 5. Cabinetry goes in Week 6. A Week 3 delivery gives Windsor 2–4 weeks of lead time before he needs any finishes on site. The timing is designed so Kimberly is never rushing and Windsor is never waiting.
Construction Sequencing Logic
Demo: All zones simultaneously - one crew, one pass, one cleanup.
MEP Rough-In: All zones in one pass - plumber and electrician touch the whole house once.
Build-Out Priority: 1 · Kitchen + Open Concept 2 · Master Bath Addition 3 · Guest Bath 1 + 2 in parallel 4 · Laundry Room 5 · Hidden Hallway Wardrobe
Glass Wall Critical Path: 90-day lead time. Order placed Day 1. Target arrival Week 6.
MEP Rough-In: All zones in one pass - plumber and electrician touch the whole house once.
Build-Out Priority: 1 · Kitchen + Open Concept 2 · Master Bath Addition 3 · Guest Bath 1 + 2 in parallel 4 · Laundry Room 5 · Hidden Hallway Wardrobe
Glass Wall Critical Path: 90-day lead time. Order placed Day 1. Target arrival Week 6.
W1
Demo All Zones Simultaneously
Kimberly Phase 1 Building Documents Delivered Day 1 · Design Selections In Progress
Phase 1 Delivery - Day 1Space planning, kitchen framing layout, master bath layout, MEP coordination drawings, elevation drawings, shop drawings → Windsor can demo and frame. Design selections (mood boards, finish inspo, 3D renders) still in progress - targeting Week 3.
Windsor - GC
🚨 Order glass panels Day 1 - 90-day lead time
Day 1: site protection - dust barriers, floor protection, utility shutoffs
Chimney and fireplace demolition - SE on site for structural sign-off
Remove chimney wall connecting kitchen and living room
Demo kitchen, guest baths 1+2, laundry - all simultaneously
⚠ Risk: Structural surprises inside chimney wall - 3–5 day buffer
◆ All demo complete by Friday
Joe - Drafter
🚨 Kitchen framing plan in Windsor's hands BEFORE demo - chimney connects to kitchen
🚨 Master bath framing plan delivered simultaneously - both spaces frame together
🚨 Full drawing set to Kimberly BEFORE Day 1 - she cannot complete her technical package without it. Joe delivers first, Kimberly incorporates, then delivers to Windsor on Day 1 FINAL
Field RFI responses from this point - 24-hour turnaround
Kimberly V - Designer
◆ DAY 1 DELIVERY: Space planning, kitchen framing layout, master bath layout, MEP coordination drawings, elevation drawings, shop drawings BUILDING DOCS
Day 1 site kickoff - walk all Phase 1 zones, confirm sequencing
Design team continuing: mood boards, finish inspo, 3D renders - targeting Week 3
Friday client update - demo happening, project is moving
W2
Structural Framing + Master Bath Framing
Windsor Building from Phase 1 Documents · Kimberly Finalizing Selections
Windsor - GC
Install structural beam/header - chimney zone
City structural inspection - beam sign-off
Frame master bath addition using Joe's framing plan
Frame glass wall rough opening and structural header
Subfloor prep in kitchen and all demo zones
⚠ Risk: Inspection scheduling - book inspector Monday morning
Joe - Drafter
Field RFI responses - 24-hour turnaround
Verify framing matches drawings after beam installation
Update drawings for any field-required structural modifications - same-day
Kimberly V - Designer
Design team finalizing: mood boards, finish inspo boards, 3D renders, lighting plan
Review Joe's full drawing set for design intent - redline deviations
Present design packages to clients - Kitchen, Master Bath, Guest Baths, Laundry
Site visit: verify framing matches design drawings + open concept intent
◆ All client design approvals in hand by end of Week 2
W3
MEP Rough-In Begins - Kimberly Phase 2 Design Selections Delivered
All Three Tracks Converge · Design Selections to Windsor Week 3 Start
Phase 2 Delivery - Week 3 StartMood boards, finish inspo boards, 3D renders, full home lighting plan - all spaces. Tile goes in Week 5, cabinetry Week 6. 2–4 weeks of lead time built in. Windsor has everything he needs.
Windsor - GC
Kitchen rough plumbing: sink, dishwasher, gas line, pot filler if applicable
Kitchen rough electrical: new circuits, under-cabinet lighting, island
Master bath: full plumbing rough-in per approved drawings + rough-in spec sheet
Guest Bath 1 + 2: plumbing rough-in
Laundry room: plumbing and electrical rough-in
Full home electrical rough-in per approved lighting plan
Order finishes from Kimberly's Phase 2 selections
Joe - Drafter
Field RFI responses - MEP subcontractors will have questions
Verify MEP rough-in matches drawings - flag conflicts same day
Revised sheets for any field MEP changes - same day REVISED
Kimberly V - Designer
◆ PHASE 2 DELIVERY: Mood boards, finish inspo boards, 3D renders, full home lighting plan - all spaces DESIGN SELECTIONS
Site visit: verify MEP rough-in matches design drawings before walls close
Flag any MEP deviation from design intent to Windsor in writing - same day
Lock all client approvals - no changes after MEP rough-in begins
W4
MEP Inspections + Insulation + Drywall
Close-In Phase
Windsor - GC
MEP rough-in inspections - schedule Monday morning
Insulation installation all zones
Drywall hanging all Phase 1 zones
Glass wall rough opening confirmed ready for window unit
⚠ Risk: Failed MEP inspection - budget 3-day correction window
◆ MEP inspections passed · Walls closing in
Joe - Drafter
Deliver confirmed full house spatial floor plan FINAL
Deliver confirmed full home lighting plan FINAL
◆ All construction deliverables complete - RFI standby only
Kimberly V - Designer
Confirm all material deliveries on track: tile, vanities, fixtures, hardware, flooring
Halfway client check-in - progress update
Stone fabricator: confirm countertop templating for Week 6
W5
Drywall Finish + Tile Begins + Wardrobe Carpenter On Site
Finishes Begin
Windsor - GC
Drywall taping, mudding, sanding - all zones
Waterproofing + backer board: master bath shower, guest bath showers
Tile: master bath shower walls + floor
Guest bath 1 + 2 tile installation
Subfloor prep for white oak flooring
Hallway wardrobe carpenter on site - built-in installation begins
Joe - Drafter
Field RFI responses - 24-hour turnaround
Waterproofing inspection documentation
Kimberly V - Designer
Site visit: tile matches approved inspo spec before grout sets
Waterproofing sign-off before tile on top
Review wardrobe carpenter progress vs shop drawings
Confirm white oak flooring on site
Friday client update
W6
Cabinetry + Glass Wall Install + Flooring Begins
Cabinetry + Millwork
Windsor - GC
Kitchen cabinetry installation
Master bath + guest bath vanity cabinet installations
Living room glass panel wall installation
White oak flooring begins - open concept zone first
Kitchen backsplash + laundry tile completion
⚠ Risk: Glass panels must arrive by Day 1 of this week
Joe - Drafter
Field RFI responses
Cabinetry cross-check vs shop drawings
Kimberly V - Designer
Cabinetry inspection vs elevations and hardware placement
Glass wall installation inspection - plumb, level, smooth operation
Stone fabricator on site - countertop field measurement all zones
Friday client update - milestone photos
W7
Countertops + Fixtures + Electrical Trim-Out + Paint
Finish Trim
Windsor - GC
Countertop installation - Calcutta Viola marble all zones
Plumbing fixture trim-out: faucets, showerheads, toilets, sinks
Electrical trim-out: switches, outlets, all lighting fixtures per plan
Door hardware throughout
White oak flooring completion all zones
Laundry room appliance connections
Prime coat then final paint - all Phase 1 zones
Joe - Drafter
Deliver final as-built drawing package to Kimberly + Windsor FINAL AS-BUILT
◆ Joe's Phase 1 deliverables closed
Kimberly V - Designer
Countertop inspection - seams, quality, overhang per spec
Verify all lighting fixtures installed per approved lighting plan
On-site paint color confirmation before final coat
Begin compiling punch list from site observations
W8
Final Paint + Punch List + Final Inspections + Client Handover
Completion
Windsor - GC
Final paint coat all Phase 1 zones
Final plumbing and electrical inspections
Punch list corrections - 48-hour window
Deep clean all Phase 1 zones
Certificate of occupancy / final inspection sign-off
Joe - Drafter
Same-day punch list drawing corrections if required
◆ Final as-built delivered to clients CLIENT COPY
Kimberly V - Designer
Full designer punch list walk - document all items with photos
Deliver punch list to Windsor in writing - 48-hour window
Joint client walkthrough with Windsor
◆ Written client final approval - triggers final payment ($7,900 due within 48 hours)
✓
Phase 1 Punch List
Final Inspection - Check Off Each Item Before Sign-Off
How to use: Kimberly walks the site and checks off each item. Anything unchecked gets delivered to Windsor in writing. Windsor has 48 hours to correct. Client signs off once all items are complete.
Kitchen
All cabinet doors align and close without resistance GC
Cabinet hardware at correct height per elevations DESIGNER
Countertop seams clean, no visible gaps or chips GC
Backsplash tile grout uniform and sealed GC
Sink faucet operational, no leaks under cabinet GC
All appliances connected, tested, operational GC
Under-cabinet lighting on correct switch and dimmer GC
Island lighting centered per approved lighting plan DESIGNER
Open concept flow reads as unified space DESIGNER
White oak flooring: no gaps, scratches, or unevenness GC
Paint lines clean at ceiling and all trim GC
Master Bath Addition
Shower tile grout sealed, no lippage between tiles GC
Shower door/glass plumb and operates smoothly GC
Showerhead height correct per approved elevation DESIGNER
Double vanity faucets operational, no leaks GC
Vanity mirrors and lighting centered per elevation DESIGNER
Toilet level, no movement, sealed to floor GC
Exhaust fan operational and vented to exterior GC
Waterproofing inspection documented in as-built DRAFTER
Floor transition to bedroom flush and clean GC
Guest Bath 1 & 2
Shower tile and grout sealed per spec GC
Vanity faucet and drain operational, no leaks GC
Toilet level and sealed to floor GC
Lighting centered on vanity wall per elevation DESIGNER
Exhaust fan vented to exterior and operational GC
Cabinet doors aligned, hardware installed GC
Paint clean at tile line and ceiling GC
Mirror centered at correct height per design DESIGNER
Laundry Room
Washer/dryer connections operational - hot, cold, drain GC
Dryer vent ducted to exterior GC
Cabinetry installed level and aligned GC
Finishes match approved design direction DESIGNER
Lighting on correct switch and operational GC
Floor finish complete and clean GC
Living Room - Glass Wall
Glass panels plumb and level in opening GC
All panels slide smoothly on track, no binding GC
Weatherstripping sealed when panels are closed GC
Structural header inspection documented in as-built DRAFTER
Interior trim around opening clean and painted GC
Floor transition at threshold flush and clean GC
Lighting per plan, dimmers functioning DESIGNER
Hidden Hallway Wardrobe
Panel reads as wall when closed - no visible gap DESIGNER
Panel opens and closes smoothly, mechanism reliable GC
Interior layout matches shop drawings DRAFTER
Interior lighting operational GC
Finish matches surrounding hallway exactly DESIGNER
No visible seam at panel edges when closed GC
Whole Home
White oak flooring: no squeaks, gaps, or surface damage throughout GC
Full home lighting plan: all fixtures operational per approved zones DESIGNER
All dimmers functioning correctly GC
Paint: no roller marks, drips, or missed spots GC
All doors open and close without sticking GC
HVAC operational in all zones, vents unobstructed GC
All final inspections passed, certificates on file GC
Final as-built package delivered to clients DRAFTER
Site deep cleaned, no construction debris remaining GC
Written client final approval collected - final payment triggered DESIGNER